The subject of the present project is the construction and equipment of the dairy and administrative part of the Troyane area on the land of Belene according to Stage II of building permit № 10 of 07.07.2016. The central part of the property between the two shepherds is envisaged building of a two-storey building with a partial basement, with a built-up area of ​​317.90sq.m. / with a basement / 691,02sq.m distributed as follows: - built-up area Dairy and administrative part-547,56m2, total built-up area - 143,46sq.m. It combines rooms specially designed for milking sheep, storage of milk, high production quality dairy products as well as the necessary premises for staff employed in the farm/
The dairy will process 1000 liters of sheep's milk a day. The milk will be harvested on the farm owned by the investor. No processing of external milks is envisaged. Within one business day, cheese and cheese will be produced on the weekly production program in Technology.
Activities
Activity Contracted Amount Reported Amount
Доставка на допълнително оборудване и товароподемна платформа: оборудване за преработка на мляко 54 076.27 0.00
Строителство на Подобект: „Мандра с административно-битова част и доилна-от Обект: Овцеферма за 800 овце-затворен цикъл напроизводство ПИ03366.180.4. гр. Белене, общ.Белене,обл.Плевен,“: Строително-монтажни дейности 182 813.89 0.00
Обзавеждане: Доставка на обзавеждане за обслужване на дейностите в предприятието 5 430.43 0.00
Доставка на технологично оборудване: оборудване за преработка на мляко 100 202.98 0.00

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.