Description

The current project of construction of the power plant 80.08 kwp for own needs on the entire building in PI 36587.502.1316, Kaspichan, district Shumen.
By realizing its investment intention, ISIS Ltd. will become a modern, high-tech enterprise, covering all requirements for applicable national and European legislation.
 Our project offers the opportunity to build an electrical center with a capacity of 80.08 kwp for own needs, which will achieve a change in production costs and will achieve a competitive price for product applicants.
Activities
Activity Contracted Amount Reported Amount
Изграждане на електрическа централа 80,08 kw/p за собствени нужди изцяло върху съществуващата сграда в ПИ 36587.502.1316, гр. Каспичан, обл. Шумен.: Изграждане на електрическа централа 80,08 kw/p за собствени нужди изцяло върху съществуващата сграда в ПИ 36587.502.1316, гр. Каспичан, обл. Шумен. 49 800.62 52 290.65

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.