Description

The planned investments include the construction of an air-conditioned production building (dairy) and technological equipment for the dairy in order to create a production line for automated production of dairy products from raw "sheep's milk". The given investments also include the installation of photovoltaic systems for the production of electricity from solar rays with a capacity of 30 kWp.
The implementation of the planned investments will enable the company the necessary way to enter more profitable markets of the dairy industry. The chosen technique for installation in the dairy meets the European standards of efficiency. With its implementation, the competitiveness of the company will be directly improved, the costs for electricity will be reduced and the final marriage will be reduced.
Additionally, the envisaged RES will enable the reduction of electricity costs by reducing the need to use energy operators for electricity distribution.
Activities
Activity Contracted Amount Reported Amount
Доставка и монтаж на ВЕИ: Доставка и монтаж на фотоволтайчна централа за производство на енергия от слънчеви лъчения с максимална мощност 30 kWp 80 528.47 0.00
Изграждане на Мандра и оборудването й: По тази дейност е предвидено, изграждане на Мандра и оборудване й с технологично оборудване, нужно за производство на кисело мляко, сирене и катък от овче мляко. 422 487.61 0.00
Управление на проекта: Да се следи за правилното изпълнение на дейностите включени в проекта, изпълнението на дейностите от избраните изпълнители. 19 940.38 0.00

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.