Description

With the implementation of the project proposal, the infrastructure will be improved in three of the settlements of the Municipality of Hajredin. There will be repairs and reconstruction of three hubs for Hayredin Streets in the villages of Hayredin, Manastirishte and Mihaylovo. Where new sidewalks are missing, new ones will be built, which will facilitate the easier movement of residents in settlements, people with permanent disabilities, to prevent the occurrence of road accidents. The project aims at reconstructing street pavements and curbs, improving the transport performance and loadability of road pavement, in order to ensure safe traffic conditions and good drainage of streets and surrounding areas.
Activities
Activity Contracted Amount Reported Amount
Строително-монтажни работи по проекта.: Строително-монтажни работи по проекта включващи улица "Кръстьо Боков " в с. Хайредин, улица "Г. ДИМИТРОВ" с. Михайлово и улица "Самуил" с.Манастирище. 0.00 530 141.13
Консултантски услуги по управление на проекта.: Управление на дейностите по проекта. 0.00 5 010.66
Строителен надзор: Осъществяване на строителен надзор по СМР на проекта. 0.00 9 970.20

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.