Total count of contracts |
4 |
Total amount of grant |
1 217 084 855.15
BGN |
Total amount |
1 225 162 146.71
BGN |
Total count of beneficiaries |
1 |
Beneficiary |
Address |
Location |
Project proposal number |
Project Name |
Total |
Grant |
Self-financing by the Beneficiary |
Duration (months) |
Status of Implementation of the Contract/Order of the Grant |
000695089 ROAD INFRASTRUCTURE AGENCY |
Bulgaria, Sofia, 1606, бул. МАКЕДОНИЯ № 3 |
|
BG16M1OP001-2.001-0001 |
Struma Motorway – Lot 3.1, Lot 3.3 and Zheleznitsa Tunnel |
742 502 905.55
|
736 765 596.57
|
5 737 308.98
|
91 |
In execution (starting date) |
000695089 Road Infrastructure Agency |
Bulgaria, Sofia, 1606, бул. МАКЕДОНИЯ № 3 |
|
BG16M1OP001-2.001-0002 |
Construction of "Kalotina-Sofia" Motorway - Lot 1 "Western arc of Sofia Ring Road (SRR)" , phase 2 |
115 671 717.60
|
115 408 769.04
|
262 948.56
|
96 |
In execution (starting date) |
000695089 Road Infrastructure Agency |
Bulgaria, Sofia, 1606, бул. "Македония" №3 |
|
BG16M1OP001-2.001-0006 |
„Burgas bypass road“
(„Burgas bypass road from km 230+700 of road I-9 Sarafovo-Burgas to km 493+550 of road I-6 Vetren-Burgas and local lanes“) |
88 401 451.13
|
88 127 299.51
|
274 151.62
|
62 |
In execution (starting date) |
000695089 Road Infrastructure Agency (RIA) |
Bulgaria, Sofia, 1606, Площад Македония № 3, София 1606, България |
|
BG16M1OP001-2.001-0005 |
Europa Motorway from km 15+500 to km 48+903 |
278 586 072.43
|
276 783 190.03
|
1 802 882.40
|
94 |
In execution (starting date) |
Notes:
Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN
Project cost information in the regions based on the latest update of the Grant contract
The information about the actually paid project amounts is not related to the respective region, but is for the whole project. It is visible when accessing each individual project, and for all projects in the sample - when exporting the data.