Programme: Programme "Competitiveness and Innovation in Enterprises" 2021-2027

Planning region: All

Description

The project of RD Systems Ltd. includes modernization and optimization of the production plant through the implementation of energy-efficient and innovative technologies. The main goal is to improve production processes, reduce energy costs and increase the competitiveness of the enterprise.

Technical implementation of the project

1. Compressor system including:

- 2 compressors with inverter control

- Power: 5.5 kW each

- With air dehumidifier

- Provides stable and effective air pressure for production needs

2. Receiver

- 1 unit, capacity 1000 liters

- Improves air pressure stability and reduces compressor cycling

3. Thermal insulation system

- Walls with EPS (expanded polystyrene)

- Area: 330 m²

- Reduces heat loss, improves the internal microclimate and increases the energy efficiency of the building

4. Water-to-water heat pumps

- 2 units

- Power: 28 kW each

- Provide effective heating and cooling of production premises with minimal energy consumption

Expected effect.

- The project of RD Systems Ltd. is based on the implementation of modern energy technologies that:

-Optimize production processes

- Reduce operating costs

- Improve the sustainability of the enterprise

The combination of inverter compressors, a large receiver, effective thermal insulation and heat pump systems will ensure long-term efficiency and reliability of the production infrastructure.
None

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.