Indicators
| Indicator |
Measure Unit |
Base Value |
Target amount |
Reached amount |
| 1. Launch of a tender for the construction of 285 MW production capacity of electricity from renewable sources (wind and solar power) co-located with 75 MW of energy storage systems |
|
No |
No |
No |
| 2. Launch of a tender for the construction of 285 MW production capacity of electricity from renewable sources (wind and solar power) co-located with 75 MW of energy storage systems |
|
No |
No |
No |
| 3. Launch of a tender for the construction of 285 MW production capacity of electricity from renewable sources (wind and solar power) co-located with 75 MW of energy storage systems |
|
No |
No |
No |
| 4. Launch of a tender for the construction of 285 MW production capacity of electricity from renewable sources (wind and solar power) co-located with 75 MW of energy storage systems |
|
No |
No |
No |
| 5. Launch of a tender for the construction of 285 MW production capacity of electricity from renewable sources (wind and solar power) co-located with 75 MW of energy storage systems |
|
No |
No |
No |
| 6. Additional new production capacity of electricity from renewable sources (wind and solar power) co-located with electricity storage capacity commissioned |
MW |
1 704.00
|
3 129.00
|
0.00
|
Notes:
Elements in light blue allow detailed view when selected