Financial Information

3 219 347.15 EUR
2 872 310.05 EUR
347 037.10 EUR
2 857 080.94 EUR
85.00 %
{point.key}
{point.value}
{point.key}

Financial Corrections

Reason % of financial
correction
Financial corrections amounts1,2 Contract
Grant Self-financing Total
Нарушения в документацията за обществени поръчки 5.00 1 559.08 174.20 1 733.28 SIP-2000 OOD
Нарушения в документацията за обществени поръчки 5.00 5 058.98 565.23 5 624.21 BT -ENGINEERING
Нарушения в документацията за обществени поръчки** 0.00 0.00 0.00 0.00 B.I.S. INJENERING
Нарушения в документацията за обществени поръчки 25.00 6 204.14 693.19 6 897.33 RUBIN KOMERS
Нарушения в документацията за обществени поръчки 25.00 1 230.25 137.46 1 367.71 RUBIN KOMERS
Нарушения в документацията за обществени поръчки** 0.00 0.00 0.00 0.00 “Balkanika Technologies“ DZZD
Нарушения в документацията за обществени поръчки 25.00 425 914.41 79 363.88 505 278.29 “Balkanika Technologies“ DZZD

Notes:

* The amount of the actual amounts paid cumulative
** The beneficiary disputes the financial correction in court in accordance with the Administrative Procedure Code.
1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.
2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.
Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.