Description

With the implementation of the project proposal, the infrastructure will be improved in three of the settlements of the Municipality of Hajredin. There will be repairs and reconstruction of three hubs for Hayredin Streets in the villages of Hayredin, Manastirishte and Mihaylovo. Where new sidewalks are missing, new ones will be built, which will facilitate the easier movement of residents in settlements, people with permanent disabilities, to prevent the occurrence of road accidents. The project aims at reconstructing street pavements and curbs, improving the transport performance and loadability of road pavement, in order to ensure safe traffic conditions and good drainage of streets and surrounding areas.
Activities
Activity Contracted Amount Reported Amount
Строително-монтажни работи по проекта.: Строително-монтажни работи по проекта включващи улица "Кръстьо Боков " в с. Хайредин, улица "Г. ДИМИТРОВ" с. Михайлово и улица "Самуил" с.Манастирище. 0.00 1 036 865.93
Консултантски услуги по управление на проекта.: Управление на дейностите по проекта. 0.00 9 800.00
Строителен надзор: Осъществяване на строителен надзор по СМР на проекта. 0.00 19 500.00

Notes:

Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN
The project is financed by the Operational Programme "Technical Assistance" and co-financed by the European Union through the European Regional Development Fund.
In implementing the project № 0115-CCU-2.1 "Information system for management and monitoring of EU funds in 2014-2020 - UMIS 2020" (BG161PO002-2.1.01-0007-C0001).