Saved trees
UMIS AND ITS USERS CONTRIBUTED TO SAVING 78 487 TREES
Български

Programme: Recovery and Resilience Plan

Planning region: All

Participating Organizations

None
Contractor legal entity Contracted Amount* Reported Amount**
180880179 PLISKA RAILWAY STATION 6 015 096.89 6 015 075.84
205677435 TRANSPORTATION CONSTRUCTION AND REHABILITATION 9 434 582.86 9 434 532.46
177522834 "ICG-KSS" CONSORTIUM 310 752.29 310 751.21
180904790 Consortium "GARA RAZGRAD" 11 082 513.75 11 082 474.95
203068713 RUBICON ENGINEERING 137 890.31 137 889.82
177432059 CONSORTIUM STRABAG RAIL 12 423 629.77 12 423 586.28
203602455 ETE ENGINEERING AD 251 143.32 251 142.44
177043855 DZZD "ETE INFRASTRUKTURA" 183 955.02 183 954.38
203676249 Infrastructure Construction 29 730 796.61 29 730 595.02
177547104 KR SVOGE 13 261 463.15 13 261 414.36
Subcontractor legal entity Contracted Amount*
202924485 OBONATO BUILD 0.00

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:
  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA
** This column represents the amount of costs claimed by the beneficiary
Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.