Saved trees
UMIS AND ITS USERS CONTRIBUTED TO SAVING 73 454 TREES
Български

Programme: Recovery and Resilience Plan

Planning region: All

Identification

BG-RRP-4.032-0240-C01
A combined project including the construction of a new capacity local electricity storage plant 430 kWh / PCS: 200 kW and - built own photovoltaic power plant with installed capacity PV 2 - 533,60 kWp at the production site of "Vipom" JSC" in property with identifier PI 10971.513.14 in Vidin, with administrative address: Vidin, Western Warehouse Zone.
815123244 Vipom JSC
176789460 MINISTRY OF ENERGY
12.02.2025
12.02.2025
31.03.2026
In execution (starting date)
Location of Performance
  • Bulgaria, North and South East Bulgaria (BG3), North-West (BG31), Vidin (BG311), Vidin, Vidin

Notes:

System.Threading.Tasks.Task`1[Microsoft.AspNetCore.Html.HtmlString] Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is financed by the Operational Programme "Technical Assistance" and co-financed by the European Union through the European Regional Development Fund.
In implementing the project № 0115-CCU-2.1 "Information system for management and monitoring of EU funds in 2014-2020 - UMIS 2020" (BG161PO002-2.1.01-0007-C0001).
System.Threading.Tasks.Task`1[Microsoft.AspNetCore.Html.HtmlString]