Description

The project proposal is for the realization of a Photovoltaic power plant for own needs with a total installed capacity of 29.7 Kw in the town of Rakovski
Activities
Activity Contracted Amount Reported Amount
10.1 Изграждане на ФЕЦ за собствени нужди с мощност 29.7 Kw: По проекта ще бъде изграден ФЕЦ за собствени нужди с мощност 29.7 Kw 91 729.57 91 729.57

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.