Programme: Recovery and Resilience Plan

Planning region: All

Description

The project proposal envisages the implementation of a combined project including:
   - construction of a new installed capacity for the production of electrical energy from solar energy - "production" component of the combined project - Construction of a photovoltaic power plant 899.460kW, located on the roofs of buildings and in adjacent terrain, in a land property with identifier 40052.28.85, in Begliko locality, Krupnik village, Simitli municipality, Blagoevgrad region and 
   - construction of local electrical energy storage facilities (ELS) - "storage" component of the combined project - container battery system for energy storage with a designed nominal power and capacity of 440kW/920kWh.
Activities
Activity Contracted Amount Reported Amount
Доставка и монтаж на 1контейнерна батерийна система за съхранение на енергия : Дейността включва доставка и монтаж на 1 бр. контейнерна батерийна система за съхранение на енергия с проектирана номинална мощност от 440kW и капацитет от 920kWh. Технически параметри: -Експлоатационен живот в цикли gt;= 6000; -Ефективност на системата за ЛСС при С/2 и пълен цикъл на заряд и разряд (включва инвертор с управление, конвертори, охлаждаща система, батерии и всички допълнителни електрически консумации) gt; 80%; -Минимален използваем капацитет на батерията на ЛСС: -при заряд gt;= 80% -при разряд lt;= 10%. 286 323.45 0.00

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.