Description

ET "Grimi - Husein Husein" carries out activities in the production and sale of livestock production - fattened pigs. The investment proposal of ET Grimi - Husein Husein is related to the modernization and increasing the sustainability of the existing agricultural holding, through the construction of autonomous photovoltaic power plants (PEC) for own needs in three land properties as follows:
Construction of an autonomous photovoltaic power plant (PEC) with a capacity of 37.62 kWp and a modular battery with a capacity of 97Wh for own needs" in PI 55155.7.84, located in the city of Pazardzhik, in the town of "Zaikovi Mandri".
Construction of an autonomous photovoltaic plant (PEC) with a capacity of 37.62 kWp and a modular battery with a capacity of 97kWh for own needs" in PI 56277.1.135 located in the city of Peshtera, in the town of "Kuriat".
"Construction of an autonomous photovoltaic power plant (PEC) with a capacity of 100.32 kWp and a modular battery with a capacity of 200kWh, for own needs" in PI 66559.5.32, located in the city of Pazardzhik, village of Sinitovo, town of "Lamburkite".
Activities
Activity Contracted Amount Reported Amount
- Изграждане на автономна ФЕЦ за собствени нужди: За нуждите на стопанството е предвидена следната материална инвестиция: - Изграждане на автономна ФЕЦ за собствени нужди Предвидената инвестиция в настоящия проект ще позволи технологичното модернизиране на земеделското стопанство, като същевременно се постигне прецизно земеделие, ефективно използване на ресурсите и опазване на компонентите на околната среда, включително за намаляване на вредните емисии 508 104.60 508 104.59

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.