The investment includes the construction of a new intermodal terminal (IMT) - that integrates different modes of transport (inland waterway, rail and road) - and its infrastructure for containers in Ruse (North Central Planning Region in Bulgaria). Ruse is a key intermodal hub/intersection (in the TEN-T core intermodal transport network under Regulation (EU) No 1315/2013 as part of the EU Rhine-Danube Transport Corridor).
The scope of the project shall cover the construction of the basic and the enabling infrastructure. The remaining loading and unloading equipment will be provided by the future terminal operator. The Bulgarian State will have ownership of the terminal infrastructure, but the National Railways Infrastructure Company shall tender the construction award.
The investment shall be completed by 31 December 2025 and the launch of the tender for the selection of the IMT operator shall be completed by 31 March 2026.
Activities
Activity
Contracted Amount
Reported Amount
Дейност 1 Планиране и проектиране: Разходи за проектиране, проучвания, анализи, стратегии, програми и т.н.
1 081 085.27
0.00
Дейност 2 Строителство: Дейността вклюва:
СМР инфраструктура
Закупуване на машини и оборудване
Непредвидени разходи
46 340 154.44
0.00
Дейност 3 Надзор по време на проектирането и строителството (оценка на съответствието, строителен надзор по ЗУТ, оценка оперативна съвместимост и оценка на риска): Разходи за тип (инвеститорски/авторски/ строителен) контрол
2 662 799.07
0.00
Дейност 4 Публичност: Осигуряване на публичност по инвестицията.
30 892.33
0.00
Дейност 5 Техническа помощ / Организация и управление: Техническа помощ / Организация и управление
1 834 501.89
0.00
Дейност 6 Избор на оператора на интермодалния терминал: Избор на оператора на интермодалния терминал чрез склюване на концесионен договор.
0.00
0.00
Notes:
Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN