Procurements

Subject to due process: Доставка и монтаж на компресор -1 бр. , Estimated Amount: 9 816.80
  • Differentiated position 1: Доставка и монтаж на компресор -1 бр.
    Contractor: BIMS LTD
    Contract total funded value: 4 908.40
Subject to due process: Доставка и монтаж на Прозрачни_ограждащи_конструкции_прозорци_и_врати - С рамка от алуминий с прекъснат топлинен мост - 84 кв.м. , Estimated Amount: 11 759.71
  • Differentiated position 1: монтаж на алуимиева дограма
    Contractor: VALENTIN PETROV 2004
    Contract total funded value: 5 879.86
Subject to due process: Доставка и монтаж на сандвич панели за стени - 610 кв.м , Estimated Amount: 78 738.95
  • Differentiated position 1: Доставка и монтаж на сандвич панели за стени - 610 кв.м
    Contractor: KAMSTROI
    Contract total funded value: 39 369.47
Subject to due process: Доставка и монтаж на Секционни индустриални врати - 16 кв.м. , Estimated Amount: 2 300.81
  • Differentiated position 1: Доставка и монтаж на Секционни индустриални врати - 16 кв.м.
    Contractor: ET KASTELO GABROWO-MARIN KUNEW-BOGDANA KUNEWA
    Contract total funded value: 1 150.41
Subject to due process: Доставка и монтаж на Топлоизолационни плочи от минерална вата - 450 кв.м. , Estimated Amount: 36 301.72
  • Differentiated position 1: Доставка и монтаж на Топлоизолационни плочи от минерална вата - 450 кв.м.
    Contractor: KAMSTROI
    Contract total funded value: 18 150.86

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.