Procurements

Subject to due process: Закупуване на ДМА 1,ДМА 2, ДМА 3 и ДМА 4, Estimated Amount: 28 730.00
  • Differentiated position 1: доставка на 1бр ДМА 1, 1бр ДМА 2, 1бр ДМА 3 и 1бр ДМА 4
    Contractor: KINTECH OOD
    Contract total funded value: 22 984.00
Subject to due process: Закупуване на материали и консумативи, Estimated Amount: 4 473.80
  • Differentiated position 1: Закупуване на материали и консумативи
    Contractor:
    Contract total funded value:
Subject to due process: Закупуване на специализирани софтуери, Estimated Amount: 10 033.59
  • Differentiated position 1: Доставка на специализирани софтуери
    Contractor: INTERNATIONAL RESOURCE MANAGEMENT EOOD
    Contract total funded value: 8 012.97
Subject to due process: Изработване на информационна табела и стикери за визуализация , Estimated Amount: 204.52
  • Differentiated position 1: Изработване на 1бр информационна табела и 4 бр стикери
    Contractor: STENDEK OOD
    Contract total funded value: 159.52
Subject to due process: Изработване на уебсайт на предприятието , Estimated Amount: 10 225.84
  • Differentiated position 1: Изработване на уебсайт на предприятието
    Contractor: Gadzhov Works LTD.
    Contract total funded value: 7 976.15
Subject to due process: Наем на офис и режийни разходи, Estimated Amount: 12 782.30
  • Differentiated position 1: Наемане на работно помещение
    Contractor: DSK Bank
    Contract total funded value: 2 780.47

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.