The investment in the construction of a new production hall and technological equipment of the enterprise imply the creation of a modern processing unit on the territory of a rural municipality. The construction of such a processing plant is very important for its location. In situational and communication terms, the chosen terrain creates conditions for building a modern-day enterprise. The site is in close proximity to existing communication systems and energy sources. From an economic point of view, the location of the new plant is characterized by all the advantages provided by the rich raw material area of fruit, water and energy resources, the place of investment coinciding with the area of organic cultivated by the applicant.
Activities
Activity
Contracted Amount
Reported Amount
Строително-монтажни работи: Дейността се състои в изграждането на нова производствена сграда, както и вертикална планировка, озеленяване и ограждане на базата.
2 614 672.81
2 744 409.41
Хладилно и технологично оборудване.: В новото хале ще бъдат закупени и разположени (съгласно технологичен и технически проект) нови технологични линии и сградни инсталации.
1 287 120.30
1 164 254.58
Notes:
Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN