Saved trees
UMIS AND ITS USERS CONTRIBUTED TO SAVING 57 332 TREES
Български

Programme: Transport and Transport Infrastructure

Planning region: All

Financial Information

12 465 847.96 BGN
12 243 326.62 BGN
222 521.34 BGN
12 810 469.12 BGN
85.00 %
{point.key}
{point.value}
{point.key}

Financial Corrections

Reason % of financial
correction
Financial corrections amounts1,2 Contract
Grant Self-financing Total
Нарушения в документацията за обществени поръчки 5.00 59 919.49 0.00 59 919.49 Informat Ltd.
Нарушения в документацията за обществени поръчки 5.00 89 928.68 0.00 89 928.68 Consortium "Ti Vi Bi - Avangard" DZZD
Нарушения в документацията за обществени поръчки 5.00 278 169.54 0.00 278 169.54 Valstron DZZD
Нарушения в документацията за обществени поръчки 5.00 109 729.64 0.00 109 729.64 NSK Sofia Sole Proprietorship OOD
Нарушения в документацията за обществени поръчки 10.00 189 240.00 9 084.00 198 324.00 Engineering - Secondary School Ivan Vazov
Нарушения в документацията за обществени поръчки 5.00 108 391.45 3 360.00 111 751.45 "ViK Bunar" EOOD
Нарушения в документацията за обществени поръчки 25.00 280 853.79 11 547.99 292 401.78 Engineering - Secondary School Ivan Vazov
Нарушения в документацията за обществени поръчки 10.00 74 976.45 0.00 74 976.45 Consortium "Ti Vi Bi - Avangard" DZZD
Нарушения в документацията за обществени поръчки 25.00 428 074.34 13 440.00 441 514.34 "ViK Bunar" EOOD
Липса на добро финансово управление 870.25 0.00 870.25 Informat Ltd.

Notes:

* The amount of the actual amounts paid cumulative
1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.
2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.
Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN
The project is financed by the Operational Programme "Technical Assistance" and co-financed by the European Union through the European Regional Development Fund.
In implementing the project № 0115-CCU-2.1 "Information system for management and monitoring of EU funds in 2014-2020 - UMIS 2020" (BG161PO002-2.1.01-0007-C0001).