The scope of the investment project is for the reconstruction of the existing water supply network along the following streets in the village of Obnova: Vasil Petleshkov St. - OK 360a - OK 369; Connection at OK370; OK 330 - OK 359, Rila St. - OK 359 - OK 353, st. Lilac-OK 353 – OK 327, st. Sergey Rumyantsev - OK 328 - OK 357, Treti Mart Street - OK 223 - OK 319, Ivan Vazov Street - OK 319 - OK 211, Rodopi Street - OK 304 - OK 334, Arda Street - OK 227 - OK 267 , Vincho Tsachev Street - OK 268 - OK 273, Maritsa Street - OK 273 - OK 274, Hristo Smirnenski Street - OK 267 - OK 268, Malchika Street - OK 110 - OK 197, Pionerska Street - OK 169 - OK 141, st. Vela Peeva-OK 79 – OK 75; OK 75 – OK 73 Vit Street-OK 54 - OK 32, Borislav Anastasov Street-OK 87 - OK 131, Stefan Karadzha Street-OK 97 - OK 28
![](/Content/img/icons/horizontal-scroll.png)
Activity | Contracted Amount | Reported Amount |
---|---|---|
Строително монтажни дейности : Изпълнението на СМР се извършва в съответствие със ЗУТ и започва след датата на подписване на Протокол за откриване на строителна площадка и определяне на строителна линия и ниво и осигурена възможност за започване на изпълнението. | 2 847 427.77 | 0.00 |
Разходи за строителен надзор: Извършване на Строителен надзор по време на изпълнение на СМР | 32 500.00 | 0.00 |
Разходи за авторски надзор: Извършване на Авторски надзор по време на изпълнение на СМР | 900.00 | 0.00 |
Консултантски услуги за управление и отчитане: Извършване на Консултантски услуги по управление и отчитане на проекта по време на неговото изпълнение | 28 000.00 | 0.00 |