The investment plan of ASPIDA Ltd. is in the scope of point 13.1.4 of the LIG "Devnya Aksakovo" Application Terms and Conditions. Eligible activities -".. other non-agricultural activities" and includes implementation of a complex project for investment initiative "Construction:"Petrol station", located in a land plot with ID 32490.51.112, by CM of the town of Izvorsko, municipality of Aksakovo, Varna district. The design capacity of the filling station is for 20,000 l of diesel and 10,000 l gasoline, as well as a gas station with 10,000 m3 of gas, a separate filling station for a quick charging of electric vehicles. It is equipped with two gasoline columns 4/2/4 for two types of fuel, two sides. The gas station is equipped with a two-sided gas cylinder with two pistols.
The complex investment project includes the following parts:
PART I: BC; PART II: Architectural; PART III: Water Supply; PART IV: EL; PART V: HV; PART VI: Technology; PART VII: Fire Safety
During the construction of the service station, the introduction of innovations will be introduced (with the equipment) with which the applicant will obtain a competitive advantage: Self Service Terminal (SST)-a device designed to serve staff without one or more gas stations with the functioning ESFM at the site; Construction of a fast-refueling station (According to the OECD, 2005), innovation is defined as the application of a new or significantly improved product (product or service) or process, a new marketing method or a new organizational method in business practice).
The charging station for the rapid charging of electric vehicles falls within the definition of a green economy as it helps to reduce carbon emissions and pollution; improves energy and resource efficiency; that meaning economy (green product).
The total investment is worth 391007.61 BGN without VAT or 469209,13 BGN with VAT.
An appointment of 6 people from the local community is planned.
The payback period of the project is 10 months.
Activities
Activity Contracted Amount Reported Amount
Строеж и оборудване на бензиностанция: Провеждане на процедура за избор на строител с три оферти Избор на строител Сключване на предварителен договор с избрания строител Сключване на окончателен договор с избрания строител Изпълнение на дейностите по строителството на бензиностанцията съгл. приложения проект: ЧАСТ I: СК ЧАСТ II: Aрхитектурна ЧАСТ III: ВИК ЧАСТ IV: EЛ ЧАСТ V: OВ ЧАСТ VI: Технология ЧАСТ VII: Пожарна безопасност Отчитане дейностите по изпълнение на проекта 199 919.02 0.00

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.