Procurements

Subject to due process: Доставка и монтаж на мостов едногредов кран с товароподемност Q= 5t и Lk= 10,50м - 1 бр., Estimated Amount: 130 379.43
  • Differentiated position 1: Доставка и монтаж на мостов едногредов кран с товароподемност Q= 5t и Lk= 10,50м - 1 бр.
    Contractor: Elektrokran-Podem Ltd
    Contract total funded value: 91 265.60
Subject to due process: Доставка и монтаж на оборудване, Estimated Amount: 127 984.99
  • Differentiated position 1: Обособена позиция 1: CNC хидравлична абкантпреса – 1 бр.
    Contractor: Polimeta C Ltd
    Contract total funded value: 61 860.18
  • Differentiated position 2: Обособена позиция 2: Лентоотрезна машина – 1 бр.
    Contractor: Polimeta C Ltd
    Contract total funded value: 61 860.18
  • Differentiated position 3: Обособена позиция 3: Зав.апарат за МИГ/МАГ заваряване – 1 бр.
    Contractor: Kammarton Bulgaria Ltd
    Contract total funded value: 27 283.40
  • Differentiated position 4: Обособена позиция 4: Зав. апарат МИГ/МАГ заваряване – 1бр;
    Contractor: Kammarton Bulgaria Ltd
    Contract total funded value: 27 283.40
  • Differentiated position 5: Обособена позиция 5: CNC Хидравлична гилотина – 1бр.
    Contractor: Polimeta C Ltd
    Contract total funded value: 61 860.18
  • Differentiated position 6: Обособена позиция 6: Плазморезателно оборудване -1 бр.
    Contractor: Kammarton Bulgaria Ltd
    Contract total funded value: 27 283.40

Notes:

Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
The project is funded by the “Technical Assistance” Programme 2021–2027, co-financed by the European Union through the European Regional Development Fund, under project BG16RFTA001-1.003-0001 “Digital transformation in the management of EU funds” and by the “National Recovery and Resilience Plan”, under Investment C10.I11 “Ensuring an adequate information and administrative environment for the implementation of the Recovery and Resilience Plan”.