Financial Information
95 190 354.12
BGN
83 101 179.11
BGN
12 089 175.01
BGN
83 101 179.11
BGN
85.00
%
Financial Corrections
Reason | % of financial correction |
Financial corrections amounts1,2 | Contract | ||
---|---|---|---|---|---|
Grant | Self-financing | Total | |||
Нарушения в документацията за обществени поръчки | 10.00 | 13 073.86 | 1 901.92 | 14 975.78 | RAYKOMERS KONSTRUKSHAN |
Нарушения в документацията за обществени поръчки | 5.00 | 2 710.66 | 394.34 | 3 105.00 | D and D Consulting Ltd. |
Нарушения в документацията за обществени поръчки | 5.00 | 3 008.05 | 437.60 | 3 445.65 | G amp; I LTD. |
Нарушения в документацията за обществени поръчки** | 5.00 | 128 767.51 | 18 732.49 | 147 500.00 | BIM Consulting Ltd. |
Нарушения в документацията за обществени поръчки** | 5.00 | 1 578 205.46 | 229 590.03 | 1 807 795.49 | Unification of Roan-Ruse /DZZD/ |
Нарушения в документацията за обществени поръчки** | 5.00 | 41 031.00 | 5 969.00 | 47 000.00 | Unification Consortium SKAD |
Нарушения в документацията за обществени поръчки** | 5.00 | 47 150.73 | 6 859.27 | 54 010.00 | Unification VODNADZOR RUSE 2019 |
Нарушения в документацията за обществени поръчки** | 0.00 | 0.00 | 0.00 | 0.00 | Unification of PODEMSTROI 2020 DZZD |
Нарушения в документацията за обществени поръчки** | 0.00 | 0.00 | 0.00 | 0.00 | Unification of ViK Ruse 2020 /DZZD/ |
Нарушения в документацията за обществени поръчки** | 0.00 | 0.00 | 0.00 | 0.00 | Unification of ViK Sredna Kula 2019 /DZZD/ |
Нарушения в документацията за обществени поръчки** | 0.00 | 0.00 | 0.00 | 0.00 | DZZD "Ruse-ViK" |
Нарушения в документацията за обществени поръчки** | 5.00 | 468.22 | 68.11 | 536.33 | MILIVA Ltd. |
Нарушения в документацията за обществени поръчки | 5.00 | 468.22 | 68.11 | 536.33 | MILIVA Ltd. |
Нарушения в документацията за обществени поръчки | 0.00 | 0.00 | 0.00 | 0.00 | Unification of ViK Ruse 2020 /DZZD/ |
Нарушения в документацията за обществени поръчки** | 0.00 | 0.00 | 0.00 | 0.00 | Unification of ViK Sredna Kula 2019 /DZZD/ |
Notes:
* The amount of the actual amounts paid cumulative
** The beneficiary disputes the financial correction in court in accordance with the Administrative Procedure Code.
1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.
2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.
Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN
** The beneficiary disputes the financial correction in court in accordance with the Administrative Procedure Code.
1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.
2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.
Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN