Identification

UMIS Number BG16FFPR003-4.015-0001-C01
Project Name Financial agreement
Beneficiary 203740812 Fund manager of financial instruments in Bulgaria
Funding JTF ==> Development of Regions Programme 2021-2027
Date of the Contract/Order 10.09.2026
Start Date 10.09.2026
End Date 31.12.2029
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Град (BG411), Столична, гр.София

Description

Brief description


                
Activities
  • Activity: Управление на предоставените с финансово споразумение средства по Приоритетет 4 „Справедлив преход“ финансови инструменти по Програма „Развитие на регионите“ 2021-2027 (ПРР) : По линия на финансовите инструменти по Приоритет 4 ще бъде подкрепен широк спектър от инвестиции, в съответствие с Териториалните планове за справедлив преход: мерки за икономическа трансформация, енергийна ефективност и смекчаване на социалните последици във въгледобивните региони в България с териториален обхват - общините в областите Кюстендил, Перник и Стара Загора, както и на общините Нова Загора, Ямбол, Симеоновград, Харманли, Тополовград, Димитровград, Хасково, Елхово, Сливен и Тунджа, Contracted Amount: 600 000 000.00 , Reported Amount: 0.00

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Additional operational capacity installed for renewable energy, Measure Unit: MW, Base Value: 0.00 , Target amount: 205.91 , Reached amount: 0.00
Indicator 2 Enterprises receiving support through financial instruments, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 228.00 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 228.00 , Reached amount: 0.00
Indicator 4 Jobs created in supported entities, Measure Unit: годишни ЕПРВ, Base Value: 0.00 , Target amount: 1 833.00 , Reached amount: 0.00
Indicator 5 Estimated greenhouse emissions, Measure Unit: тонове еквивалент на CO2/година, Base Value: 0.00 , Target amount: 8 635.78 , Reached amount: 0.00
Indicator 6 Additional production capacity for renewable energy (of which: electricity, thermal) , Measure Unit: MW, Base Value: 0.00 , Target amount: 293.00 , Reached amount: 0.00
Indicator 7 Total renewable energy produced (of which: electricity, thermal), Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 386 198.43 , Reached amount: 0.00

Financial Information

Total Project cost 600 000 000.00 EUR
Grant 600 000 000.00 EUR
Self amount 0.00 EUR
Total actual amounts paid 180 000 000.00 EUR
Percentage of EU co-financing 81.74 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN