| UMIS Number | BG16RFPR001-1.003-0118-C01 |
| Project Name | Increasing the innovative capacity and competitiveness of BULARMEX-IK JSCo by implementing a production innovation for a wedge-shaped gate valve of forged steel with a monolithic flexible wedge and putting into operation high-tech machines for its production |
| Beneficiary | 201009335 BULARMEX - IK |
| Funding | ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027 |
| Date of the Contract/Order | 09.12.2024 |
| Start Date | 09.12.2024 |
| End Date | 09.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение ще удовлетвори потребността от внедряването на производствената иновация на нов, частично превъзхождащ досега известните видове , клиновиден шибър от кована стомана с монолитен гъвкав клин. Ще бъде удовлетворена и потребността от повишаване капацитета на производство, повишаване на производителността и намаляване на производствените разходи; ще способства за въвеждане на кръгови модели за използване на ресурсите и внедряване на неутрални по отношение на климата методи и технология за производство иновативния клиновиден шибър от БУЛАРМЕКС-ИК АД. Предвижда се да бъде изпълнена една дейност за закупуване и въвеждане в експлоатация на вертикален център с ЦПУ - 1 брой, CNC струг - 1 брой и на 35-градусов наклонен инструментален струг тип CNC- 2 броя. С тези високотехнологични машини се решава проблемът за неефективната употреба на суровините в етапа на обработване на корпусните детайли на внедрявания клиновиден шибър. Това е дисбалансът между количествата входящи суровини и количеството суровини, вложени в произведените продукти, който води до генериране на големи производствени отпадъци, а и технологичен брак. По-важни преки резултати: 1) Осигуряване на необходимите високотехнологични ДМА за производство на внедрения полезен модел на иновативния клиновиден шибър от кована стомана с монолитен гъвкав клин. 2) Повишаване на производствения капацитет чрез модернизация на машинния парк в посока разширяване и технологични възможности за качествена и с висока точност обработка на корпусни детайли. 3) Подобряване значително ресурсната ефективност на предприятието чрез намаляване след изпълнение на проекта на брака от до 5% до под 1% и на количествата механични отпадъци с 15,1% на единица продукция. Това ще доведе до намаляване въглеродния отпечатък и ще намали производствените разходи. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Private investment matching public support (grants, financial instruments), Measure Unit: евро, Base Value: 0.00 , Target amount: 138 073.05 , Reached amount: 0.00 |
| Indicator 2 | Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 4 | SMEs innovating in-house, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 5 | SMEs which have introduced product or process innovation in thematic area "Clean Technologies, Circular and Low Carbon Economy" of ISSS, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 6 | SMEs introducing organizational or marketing innovation, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 276 141.86 EUR |
| Grant | 138 070.93 EUR |
| Self amount | 138 070.93 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 82.68 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на оборудване по обособени позиции:
ОП1 - Вертикален център с ЦПУ - 1 бр.;
ОП2 - CNC струг – 1 бр.;
ОП3 - Инструментален струг тип CNC с наклонено легло - 2 бр.
,
Estimated Amount: 276 141.86
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN