Identification

UMIS Number BG16RFPR001-2.004-2654-C01
Project Name Increasing the energy efficiency of Astrade Varna EOOD
Beneficiary 200105327 Astrade Varna EOOD
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 20.04.2026
Start Date 20.04.2026
End Date 20.04.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Варна (BG331), Варна, гр.Варна

Description

Brief description
Проектното предложение на „Астрейд Варна“ ЕООД е насочено към повишаване на енергийната ефективност и устойчивостта на производствените процеси на компанията , чрез внедряване на енергийно ефективно оборудване.
Инвестицията предвижда закупуване и въвеждане в експлоатация на два компресора за сгъстен въздух с инверторно управление с изсушител с мощност 11 kW и  2 броя ресивъра по 250 литра.
Реализирането на проекта ще позволи оптимизация на енергопотреблението при работата на високоенергоемкото оборудване в производството и ще оптимизира енергийната консумация в работния процес.  
Инвестицията е съобразена с принципа за „ненанасяне на значителни вреди“ върху околната среда и подкрепя постигането на националните цели в областта на енергийната ефективност. Проектното предложение е в унисон и с принципите на равнопоставеност и равни възможности за всички. В резултат от изпълнението на проекта „Астрейд Варна“ ЕООД ще постигне значителни енергийни спестявания, ще повиши конкурентоспособността си и ще осигури условия за дългосрочен устойчив растеж.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 11 388.51 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 32 538.59 EUR
Grant 21 150.08 EUR
Self amount 11 388.51 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes: