Identification

UMIS Number BG16RFPR001-2.004-1228-C01
Project Name Improving energy efficiency at Ferrit Ltd.
Beneficiary 115667666 FERIT
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 01.06.2026
Start Date 01.06.2026
End Date 01.06.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Марица, с.Войводиново

Description

Brief description
Проектното предложение на „ФЕРИТ“ ЕООД предвижда изграждане на фотоволтаична електрическа централа с инсталирана мощност на инвертора 30 kW, в комбинация с локални съоръжения за съхранение на енергия (батерии), предназначени за задоволяване на собствените енергийни нужди на предприятието.
Инвестицията е насочена към намаляване на енергийните разходи и въглеродния отпечатък на дружеството, като подпомага прехода към устойчиво и енергийно ефективно производство.

Основната дейност на дружеството е производство на плетена оградна мрежа, както и търговия с метални оградни елементи и аксесоари (код на икономическа дейност 25.93 – Производство на изделия от тел, вериги и пружини).
Проектът ще допринесе за повишаване на конкурентоспособността на предприятието, чрез използване на възобновяема енергия от слънцето, както и за съответствие с принципа за „ненанасяне на значителни вреди“ върху околната среда, в съответствие с целите на Програма „Конкурентоспособност и иновации в предприятията“ 2021–2027.

Реализирането на проекта ще осигури по-ефективно управление на енергийните ресурси, намаляване на зависимостта от външни доставчици на електроенергия и стабилност в производствената дейност на ФЕРИТ ЕООД.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 20 915.70 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 41 831.40 EUR
Grant 20 915.70 EUR
Self amount 20 915.70 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN