Identification

UMIS Number BG16RFPR001-2.004-1062-C01
Project Name “Design and Construction of a Photovoltaic Power Plant with Battery Storage and Inverter System”
Beneficiary 204471012 "DOMINO 4" Ltd.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 05.05.2026
Start Date 05.05.2026
End Date 05.05.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Варна (BG331), Варна, гр.Варна

Description

Brief description
Фирма „Домино 4“ ООД  сe помещава в ресторант на територията на гр. Варна и възнамерява, чрез реализацията на настоящия проект, да повиши енергийната си ефективност в тази сграда посредством изграждане на фотоволтаична централа.

Дружеството цели да постигне намаляване на консумацията на електрическа енергия, което от своя страна ще доведе до съществено ограничаване на емисиите на CO₂. В резултат ще се реализира повишаване на конкурентоспособността на предприятието „Домино 4“ ООД, чрез подобряване на енергийната ефективност, което ще допринесе за по-устойчив растеж, понижаване на енергийната интензивност, намаляване на производствените разходи и повишаване на екологичната съобразност на дейността.

Значителното покачване на цената на електрическата енергия през последните години затруднява нормалното функциониране на икономическата дейност на дружеството.
Като небитов краен потребител, фирмата е изправена пред перспективата за по-високи сметки за електроенергия във време, когато това може неблагоприятно да се отрази на нейното икономическо възстановяване и развитие.

Технически параметри на проекта

Проектът предвижда проектиране и изграждане на фотоволтаична централа с инсталирана мощност от 50 kW, оборудвана с батерийна система за съхранение на енергия и инверторна система за управление и преобразуване на електроенергията.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 24 401.65 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 69 719.00 EUR
Grant 45 317.35 EUR
Self amount 24 401.65 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN