Identification

UMIS Number BG16RFPR001-2.004-1095-C01
Project Name Construction of a new photovoltaic power plant for own consumption in combination with solar panels, inverters, batteries and other components necessary for the operation of the plant.
Beneficiary 115736806 NTT-3
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 01.06.2026
Start Date 01.06.2026
End Date 01.06.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Пловдив, гр.Пловдив

Description

Brief description
Монтаж на фотоволтаична електрическа централа 53.76kWp за производство на енергия от възобновяеми източници за собствено потребление в комбинация с локални съоръжения за съхранение на енергия (батерии) върху покрив на съществуваща складова база в УПИ 383.628, скл. Дейност и жил. застрояване, м. „Коматевско шосе", Район Южен, гр. Пловдив.
Централата ще служи изцяло за покриване на собствените нужди на  складовата база с електрическа енергия. Системата се състои 2 бр. соларни инвертори с номинална АС мощност P=25kW, 2 бр. литиево-йонна батерия, с капацитет по 28.8kWh. Фотоволтаичните панели са 112 бр. монокристални, всеки с номинална мощност 480Wp, с обща инсталирана мощност Ppv=53.76kWp. Фотоволтаичните панели са разположени изцяло на покрива на съществуваща сграда с ИД 56784.383.628.3, на складовата база. Фотоволтаичната централа за собствени нужди ще допринесе за по-голяма рентабилност и по-малка зависимост от цената на електрическа
енергия. Чрез ФЕЦ  складовата база сериозно намаля енергийните си разходи. Внедряването на соларни инсталации има както икономически, така и екологични ползи. Изграждането на мощности за зелена енергия е част от пакета мерки на Европейската комисия, включени в т.нар. „Зелена сделка“, чиято цел е намаляване на въглеродния отпечатък до 2050 г.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 24 401.65 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 69 719.00 EUR
Grant 45 317.35 EUR
Self amount 24 401.65 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN