Identification

UMIS Number BG16RFPR001-2.004-1472-C01
Project Name Increasing the energy efficiency of Touriststroy - Tsaratsovo Ltd.
Beneficiary 115010460 TOURISTSTROY -TSARATSOVO Ltd.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 27.03.2026
Start Date 27.03.2026
End Date 27.03.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Марица, с.Царацово

Description

Brief description
"Туристстрой - Царацово" ЕООД е модерно предприятие с основна дейност производство на метални изделия и конструкции от листов метал с приложение в машиностроенето, уредостроенето и строителството (код по КИД-2008: 25.99 "Производство на други метални изделия, некласифицирани другаде"). 
В рамките на проекта, дружеството планира да повиши енергийната ефективност на производството си като внедри следните инвестиции: 
1) ТОПЛОИЗОЛАЦИОННА СИСТЕМА ОТ САНДВИЧ ПАНЕЛИ С ТОПЛОИЗОЛАЦИЯ ОТ PIR (ПОЛИИЗОЦИАНУРАТ) ЗА ВЪНШНИ СТЕНИ - 385 кв.м. (съгласно Раздел 12 "Енергийно - ефективни изолационни системи в сгради" на Приложение 4.1 "Списък на допустимите категории активи в областта на енергийната ефективност и използването на енергия от възобновяеми източници");
2) ПРОЗРАЧНИ ОГРАЖДАЩИ КОНСТРУКЦИИ (ПРОЗОРЦИ) С РАМКА ОТ АЛУМИНИЙ И ПРЕКЪСНАТ ТОПЛИНЕН МОСТ - 97,6 кв.м. (съгласно Раздел 12 "Енергийно - ефективни изолационни системи в сгради" на Приложение 4.1 "Списък на допустимите категории активи в областта на енергийната ефективност и използването на енергия от възобновяеми източници");
3) ЕНЕРГОСПЕСТЯВАЩИ ОСВЕТИТЕЛИ (КАМБАНИ - ПРОЖЕКТОРИ) с мощност от 100W - 7 бр. (съгласно Раздел 13 "Енергоспестяващи осветители" на Приложение 4.1 "Списък на допустимите категории активи в областта на енергийната ефективност и използването на енергия от възобновяеми източници");
Внедряването на новите енергоефективни решения ще допринесе за успешното подобряване на енергийната ефективност на производствената дейност на фирмата, с което ще се ускори качествения преход към климатична неутралност чрез измеримо намаляване на въглеродния отпечатък, както и ще бъде оптимизирана енергийната консумация. 
Планираните инвестиции са изцяло съобразени с хоризонталните принципи, съгласно чл. 9 от Регламент (ЕС) № 2021/1060, както и с принципа за „ненанасяне на значителни вреди" върху околната среда и постигането на климатична устойчивост, допринасяйки за екологичния преход в дейността на предприятието.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 27 524.69 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 78 641.97 EUR
Grant 51 117.28 EUR
Self amount 27 524.69 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Процедура № 1: Изпълнение на строително – монтажни работи (СМР) по подобряване на енергийната ефективност в производствената база на „Туристстрой – Царацово“ ЕООД, Estimated Amount: 78 641.97
  • Differentiated position 1: Изпълнение на строително – монтажни работи (СМР) по подобряване на енергийната ефективност в производствената база на „Туристстрой – Царацово“ ЕООД
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN