| UMIS Number | BG16RFPR001-2.004-1439-C01 |
| Project Name | “Modernization of the energy infrastructure of ‘RIO-2012’ Ltd. – enhanced energy efficiency and own green electricity generation.” |
| Beneficiary | 202119286 RIO - 2012 Ltd |
| Funding | ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027 |
| Date of the Contract/Order | 01.06.2026 |
| Start Date | 01.06.2026 |
| End Date | 01.06.2027 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът на „РИО-2012“ ЕООД цели модернизация на енергийната инфраструктура в склада на адрес гр. Русе, бул. „Трети март“ 64 (250 кв.м, от които ~20 кв.м офис). Потребността произтича от високи енергийни разходи, остаряло осветление, „студена“ алуминиева дограма и непълноценно използване на наличните ВЕИ (PV ~17.98 kWp; инвертор 20 kW; батерии 6×5.1 kWh), което ограничава енергийната независимост и качеството на микроклимата. Целеви групи: служителите (подобрени условия на труд), предприятието и клиентите му (по-ниски разходи и по-надеждни доставки), местната общност и околната среда (по-ниски емисии). Обща цел: повишаване на енергийната ефективност и дела на енергията от ВЕИ. Специфични цели: (1) намаляване на крайното енергопотребление чрез подмяна на осветление и дограма; (2) увеличаване на собственото зелено електропроизводство чрез разширяване на фотоволтаичната система и капацитета за съхранение; (3) устойчив микроклимат чрез високоефективна термопомпа въздух–въздух. Основни дейности: подмяна на 15 линейни и 6 панелни осветителя с LED; подмяна на прозорци/врати с алуминиева дограма с прекъснат термомост; разширяване на PV с нови панели и инвертори; добавяне на батерии (и необходимите инвертори) за повишен капацитет и изместване на товара; внедряване на термопомпена система за отопление и охлаждане. Очаквани резултати: намалена консумация от мрежата и енергоинтензивност, по-висок дял на собствена зелена енергия и използване в неслънчеви часове, стабилен микроклимат и по-ниски емисии парникови газове, което повишава конкурентоспособността на фирмата. Всички мерки са съобразени с приоритетите и изискванията на процедура BG16RFPR001-2.004, включително допустимост на дейностите и индикаторите за резултат. |
| Activities | None |
| Partners | None |
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 17 799.85 , Reached amount: 0.00 |
| Indicator 3 | Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 50 856.72 EUR |
| Grant | 33 056.87 EUR |
| Self amount | 17 799.85 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 81.16 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка и монтаж на енергийно ефективни прозрачни ограждащи конструкции за повишаване на енергийната ефективност на обекта на „РИО-2012“ ЕООД.,
Estimated Amount: 8 674.85
|
| Procedure 2 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на високоефективна термопомпена система въздух–въздух за отопление и охлаждане на обекта на „РИО-2012“ ЕООД.,
Estimated Amount: 0.00
|
| Procedure 3 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на оборудване за разширяване на фотоволтаична система и система за съхранение на електрическа енергия за собствено потребление.,
Estimated Amount: 32 517.85
|
| Procedure 4 |
Subject to due process: Закупуване и доставка на енергоспестяващи LED осветителни тела – 15 бр. линейни осветители и 6 бр. LED панели/луни, включително необходимите крепежни елементи, аксесоари и съпътстващи компоненти съгласно одобрения проект.,
Estimated Amount: 3 388.94
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN