Identification

UMIS Number BG16RFPR001-2.004-1116-C01
Project Name Improving the energy efficiency of Metalstroy Engineering 95 Ltd
Beneficiary 821166385 "Metalstroy engineering 95" EOOD
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 01.06.2026
Start Date 01.06.2026
End Date 01.05.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Монтана (BG312), Монтана, гр.Монтана

Description

Brief description
Проектното предложение предвижда изграждане на фотоволтаична електрическа централа (ФЕЦ) с инсталирана мощност 56 kW и система за съхранение на енергия (батерия) с капацитет 56 kWh, която ще бъде монтирана върху покрива на производствения цех на „Металстрой Инженеринг 95“ ЕООД, находящ се в гр. Монтана, бул. „Трети март“ №147А.
Проектът има за цел да осигури енергия за собствено потребление, като по този начин се намалят разходите за закупувана електроенергия и зависимостта от външни доставчици. Реализацията на инвестицията ще доведе до значително подобряване на енергийната ефективност, намаляване на въглеродните емисии и повишаване на устойчивостта на предприятието.
Очаква се централата да произвежда приблизително 70 000 kWh електроенергия годишно, което ще покрива около 70–75% от годишното потребление на обекта. Това ще осигури годишна икономия на разходи за електроенергия  и ще доведе до намаляване на въглеродните емисии с около 50 тона CO₂ годишно.
Чрез реализирането на проекта „Металстрой Инженеринг 95“ ЕООД ще постигне по-голяма енергийна независимост, по-ниска себестойност на продукцията и подобрена конкурентоспособност на вътрешния и международния пазар
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 27 329.84 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 78 085.27 EUR
Grant 50 755.43 EUR
Self amount 27 329.84 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN