| UMIS Number | BG16RFPR001-1.008-0360-C01 |
| Project Name | Implementation of Industry 4.0 technologies in "Popchev stone design" LTD |
| Beneficiary | 103750816 POPCHEV STONE DESIGN LTD |
| Funding | ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027 |
| Date of the Contract/Order | 05.08.2026 |
| Start Date | 05.08.2026 |
| End Date | 05.11.2027 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
"Попчев стоун дизайн" ЕООД е средно предприятие, развиващо дейност в сектор C Преработваща промишленост, код по КИД 2008 23.70 Рязане, профилиране и обработване на строителни и декоративни скални материали. Проектното предложение на „Попчев Стоун Дизайн“ ЕООД е насочено към повишаване на дигиталната и технологична ефективност на производствената дейност чрез внедряване на технологии от областта на Индустрия 4.0, в съответствие с основната цел на процедура BG16RFPR001-1.008 „Въвеждане на технологии от областта на Индустрия 4.0 в предприятията“ – повишаване нивото на цифровизация в малките и средни предприятия. Проектът обхваща интегрирано внедряване на четири технологични компонента, които са ключови за цялостна трансформация на производствените процеси в модерно, конкурентоспособно и автоматизирано предприятие: - Интеграция на CAD/CAM софтуер - Проектиране и изработка на система за сканиране и оразмеряване на входни суровини - Разработка на индивидуална MES система - Закупуване на автоматизирана роботизирана поточна линия за шлайфане и полиране, с вградени IIoT и CPS технологии за мониторинг, контрол и адаптивно реагиране спрямо параметрите на производството. Посочените инвестиции осигуряват преминаване към цифрово интегрирани производствени процеси, повишаване на автоматизацията, намаляване на човешкия фактор в рутинни операции и внедряване на средства за анализ на данни и вземане на решения в реално време. Чрез прилагане на съвременни технологии от Индустрия 4.0 предприятието ще подобри производителността, проследимостта и ефективността на процесите, както и ще укрепи своята позиция на пазара. Цялостната трансформация подпомага изпълнението на стратегическите цели на фирмата за цифрова модернизация и устойчив растеж на производствената база в гр. Враца чрез внедряване на решения, които са съобразени с изискванията за цифрова стратегия, цифрова готовност и ефективност на технологичните процеси. |
| Activities |
|
| Partners | None |
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | SMEs achieving 3 or 4 digitalization level according to the maturity Index - Industry 4.0, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 4 | Private investment matching public support (grants, financial instruments), Measure Unit: евро, Base Value: 0.00 , Target amount: 434 598.10 , Reached amount: 0.00 |
| Indicator 5 | SMEs staff completing training for skills for Industry 4.0, Measure Unit: служители, Base Value: 0.00 , Target amount: 5.00 , Reached amount: 0.00 |
| Indicator 6 | Value of digital services, products and processes developed for enterprises, Measure Unit: евро, Base Value: 0.00 , Target amount: 869 196.19 , Reached amount: 0.00 |
| Total Project cost | 869 196.19 EUR |
| Grant | 434 598.09 EUR |
| Self amount | 434 598.10 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 81.92 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка на CAD/CAM софтуер - 1 бр.,
Estimated Amount: 14 801.90
|
| Procedure 2 |
Subject to due process: Доставка на Автоматична роботизирана поточна линия за шлайфане и полиране - 1 бр.,
Estimated Amount: 830 389.14
|
| Procedure 3 |
Subject to due process: Доставка на Машина за сканиране на входните суровини - 1 бр.,
Estimated Amount: 12 403.94
|
| Procedure 4 |
Subject to due process: Доставка на Система за управление на производството MES - 1 бр.,
Estimated Amount: 11 601.21
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN