Identification

UMIS Number BG16RFPR001-2.004-2787-C01
Project Name Construction of a photovoltaic power plant (including solar panels, inverters, batteries and other components) in a pasta production workshop in the town of Asenovgrad
Beneficiary 206686259 DEJA VU 93 ltd
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 14.04.2026
Start Date 14.04.2026
End Date 14.04.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Асеновград, гр.Асеновград

Description

Brief description
Проектът предвижда изграждане на фотоволтаична електрическа централа с инсталирана мощност 40 kW върху покрива на съществуващ цех  за производство на тестени изделия в гр. Асеновград. Системата ще включва соларни панели 20kW, инвертор с мощност 40 kW, както и батерии за съхранение на енергията с капацитет 40 kWh.

Основната цел на проекта е осигуряване на собствено електрозахранване чрез използване на възобновяем енергиен източник, намаляване на разходите за електроенергия и ограничаване на въглеродните емисии. Произведената електроенергия ще се използва основно за нуждите на обекта, а излишната енергия ще се съхранява в батериите за последващо потребление.

Проектът допринася за повишаване на енергийната ефективност, устойчивото развитие и прилагането на зелени технологии в сектора на услугите.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 19 521.32 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 55 775.20 EUR
Grant 36 253.88 EUR
Self amount 19 521.32 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN