Identification

UMIS Number BG16RFPR001-2.004-2189-C01
Project Name “Modernization of the production building for energy efficiency and climate resilience”
Beneficiary 200435983 The Point Stone
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 14.04.2026
Start Date 14.04.2026
End Date 14.04.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Търговище (BG334), Търговище, с.Васил Левски

Description

Brief description
Сградата, в която предприятието осъществява основната си дейност по рязане и обработване на строителни и декоративни скални материали, е построена преди повече от 40 години и оттогава не е извършван основен ремонт. Една част от покривната конструкция е ламарина, а другата – етернитови плоскости. Покривът е амортизиран и не осигурява необходимата топло- и хидроизолация. Допълнително прозорците на сградата  са  с липсващи стъкла, което прави помещенията неотопляеми. Металната входна врата на производственото помещение също е остаряла и  деформирана. Настоящото състояние на сградата води до високи енергийни загуби.

Основната цел на проекта е да се подобри енергийната ефективност на производствената сграда чрез:
•	частична подмяна на съществуващото покривно покритие с енергийно ефективни сандвич панели с полиуретан;
•	подмяна на 16 броя прозорци с нови PVC;
•	подмяна на стара метална врата на производственото помещение с нова  плътна врата;

Целева група:
Служителите на предприятието, които ще работят в енергийно ефективна среда, както и самата фирма – като ползвател на резултатите от подобрената инфраструктура и намалените енергийни разходи.

Основни дейности:
• Демонтаж и безопасно обезвреждане на съществуващото азбестсъдържащо покритие;
• Доставка и монтаж на нови енергийно ефективни сандвич панели с полиуретан;
• Подмяна на 16 броя прозорци с нови PVC дограми с висока енергийна ефективност;
• Подмяна на старата метална врата с нова плътна врата;

Очаквани резултати:
•   Частично подменени покрив, прозорци и врати;
•  Подобряване на изолацията на сградата;
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 20 462.19 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 58 463.40 EUR
Grant 38 001.21 EUR
Self amount 20 462.19 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на прозрачни ограждащи конструкции-прозорци и врата -секционна индустриална врата/външна плътна врата , Estimated Amount: 13 924.56
Procedure 2 Subject to due process: Доставка и монтаж на топлоизолационни системи от сандвич панели за покриви , Estimated Amount: 44 538.84

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN