Identification

UMIS Number BG16RFPR001-2.004-1791-C01
Project Name Enhancing Energy Independence and Production Competitiveness through Renewable Energy at Coriantro Ltd.
Beneficiary 203873855 Coriantro Ltd.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 01.06.2026
Start Date 01.06.2026
End Date 01.06.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Стара Загора (BG344), Стара Загора, с.Памукчии

Description

Brief description
Проектът има за цел изграждане на фотоволтаична електроцентрала с мощност 18 kWp на територията на производственото съоръжение на компанията, с цел намаляване на разходите за електроенергия и подобряване на конкурентоспособността на чуждестранните пазари.

Като производител, ориентиран изцяло към износ, компанията се сблъсква с високи енергийни разходи на свободния пазар, които значително влияят върху цените на производството. Въвеждането на собствен източник на възобновяема енергия ще осигури стабилно, евтино електричество, ще намали зависимостта от външни доставчици и ще повиши пряко конкурентоспособността на българските продукти в чужбина.

Компанията в момента се намира в етап на технологична модернизация и разширяване, включително увеличаване на капацитета за съхранение на семе от кориандър и обновяване на оборудването за преработка, пакетиране и фумигация. 

Въпреки това, ограничените финансови ресурси налагат постепенно инвестиране. Соларната инсталация представлява стратегическа първа стъпка към устойчива модернизация, позволявайки на предприятието да пренасочи бъдещите спестявания към подобрения в производството.

Планираната система ще бъде монтирана на земята в рамките на съществуващата площ от 20 м × 3 м по оградата на обекта, състояща се от два реда слънчеви панели, ориентирани на юг и свързани към вътрешната електрическа мрежа. Тя ще удвои наличното в момента електрозахранване (от 14,5 kW до над 30 kW), покривайки значителна част от нуждите от енергия на цеха.
Целеви групи: служителите и клиентите на компанията, които се възползват от подобрена стабилност на производството и конкурентоспособност.
Очаквани резултати: намалени енергийни разходи, повишена енергийна независимост, по-висока продуктивност и по-нисък въглероден отпечатък, повишена конкурентност на продукта на външни пазари.
Основни дейности: техническо проектиране, снабдяване и инсталиране на фотоволтаично оборудване за осигуряване на собствени нужди.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 8 784.59 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 25 098.84 EUR
Grant 16 314.25 EUR
Self amount 8 784.59 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Изграждане на фотоволтаична електрическа централа за нуждите на Кориантро ООД, във връзка с изпълнението на проект "Подобряване на енергийната независимост и конкурентоспособността на производството чрез възобновяема енергия в Кориантро ООД с Договор № BG16RFPR001-2.004-1791-C01, от 01.01.2026 г. по процедура BG16RFPR001-2.004 „Енергийна ефективност и използване на енергия от възобновяеми източници в предприятията“, финансиран по ОП "Конкурентоспособност и иновации в предприятията" 2021-2027., Estimated Amount: 25 098.84
  • Differentiated position 1: Проектиране, доставка на оборудване, строително-монтажни работи (СМР), административно узаконяване, пускане в експлоатация и гаранционна поддръжка на хибридна фотоволтаична електроцентрала (ФЕЦ) с пикова мощност 18 kWp за собствени нужди, със система за съхранение на енергия (батерии) и пълно ограничаване на връщането към мрежата (Zero Export).
    Contractor:
    Contract total funded value:
  • Differentiated position 2: Проектиране, доставка на оборудване, строително-монтажни работи (СМР), административно узаконяване, пускане в експлоатация и гаранционна поддръжка на хибридна фотоволтаична електроцентрала (ФЕЦ) с пикова мощност 18 kWp за собствени нужди, със система за съхранение на енергия (батерии) и пълно ограничаване на връщането към мрежата (Zero Export).
    Contractor:
    Contract total funded value:
  • Differentiated position 3: Проектиране, доставка на оборудване, строително-монтажни работи (СМР), административно узаконяване, пускане в експлоатация и гаранционна поддръжка на хибридна фотоволтаична електроцентрала (ФЕЦ) с пикова мощност 18 kWp за собствени нужди, със система за съхранение на енергия (батерии) и пълно ограничаване на връщането към мрежата (Zero Export).
    Contractor:
    Contract total funded value:
Procedure 2 Subject to due process: Провеждане на процедура за избор на изпълнител за доставка на компоненти за хибридна ФЕЦ 18 kWp с батерии, включително услуги по проектиране, монтаж и узаконяване., Estimated Amount: 25 000.00
  • Differentiated position 1: Проектиране, доставка на оборудване, СМР и узаконяване на хибридна ФЕЦ 18 kWp с батерии за собствени нужди
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN