| UMIS Number | BG16RFPR001-1.004-0272-C01 |
| Project Name | Improving the production capacity and increasing the competitiveness of the family enterprise "Kolio Kolev SK" OOD |
| Beneficiary | 201140612 KOLIO KOLEV SK Ltd |
| Funding | ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027 |
| Date of the Contract/Order | 14.07.2025 |
| Start Date | 14.07.2025 |
| End Date | 14.04.2026 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Настоящото проектно предложение предвижда подобряване на производствения капацитет и увеличаване на производителността на семейно предприятие "Кольо Колев СК" ООД, чрез придобиването на активи и инструменти за производствения процес на мебели. Предвижда се закупуването на три дълготрайни материални актива - високопроизводителни, прецизно работещи, специализирани машини, с които да се подобри производствения капацитет и да се повиши конкурентоспособността на микро предприятието, в което работят баща и син, и произвеждат мебели повече от 20 години. Чрез инвестициите, които ще се реализират по настоящата процедурата на програма "Иновации и конкурентоспособност" 2021-2027 г., микро предприятието ще получи шанс, който до този момент не е получавало и ще си осигури възможност да разработва нови крайни продукти и услуги, ще разшири обхвата на дейността си в условията на все по-нарастваща конкуренция и по-специфични изисквания на клиентите. С новозакупеното оборудване ще се създадат условия за разширяване на асортимента на произвежданите изделия и ще се оптимизира процеса по тяхното монтиране за крайния клиент, което в своята съвкупност ще доведе до създаване на приемственост на семейния бизнес, устойчивост и разширяване на пазарните позициите на "Кольо Колев СК" ООД. Реализираните инвестиии ще направят възможно удължаването на периода на експлоатация на мебелите, което ще доведе до намаляване на изхвърлянето на едро габаритни отпадъци. По този начин проектът ще осигури прилагането на кръгови модели по отношение на дейността, за която е заявена подкрепата. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Indicator 2 | Private investment matching public support (grants, financial instruments), Measure Unit: евро, Base Value: 0.00 , Target amount: 5 586.95 , Reached amount: 5 511.36 |
| Indicator 3 | Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Total Project cost | 21 804.39 EUR |
| Grant | 16 353.30 EUR |
| Self amount | 5 451.09 EUR |
| Total actual amounts paid | 16 353.30 EUR |
| Percentage of EU co-financing | 81.67 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Избор на изпълнител за консултантски услуги за подготовка на проектното предложение по процедура BG16RFPR001-1.004 "Подкрепа за семейните предприятия, предприятията от творческите индустрии и занаятите".,
Estimated Amount: 1 508.31
|
| Procedure 2 |
Subject to due process: Изработка и доставка на производствено оборудване за нуждите на "Кольо Колев СК" ООД по договор № BG16RFPR001-1.004-0272-СО1,
Estimated Amount: 20 839.13
|
| Procedure 3 |
Subject to due process: Изработка и доставка на производствено оборудване за нуждите на "Кольо Колев СК" ООД по договор № BG16RFPR001-1.004-0272-СО1,
Estimated Amount: 20 839.13
|
| Procedure 4 |
Subject to due process: Изработка и доставка на производствено оборудване за нуждите на "Кольо Колев СК" ООД по договор № BG16RFPR001-1.004-0272-СО1
ОП2,
Estimated Amount: 2 036.37
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN