Identification

UMIS Number BG16RFPR001-2.004-2180-C01
Project Name Construction of a photovoltaic power plant (PVPP) consisting of photovoltaic modules, batteries, and inverters for the needs of the warehouse base of VANGELOV OIL Ltd. in Vratsa.
Beneficiary 106529082 VANGELOV OIL OOD
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 05.05.2026
Start Date 05.05.2026
End Date 05.05.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Враца (BG313), Враца, гр.Враца

Description

Brief description
КандидатътВАНГЕЛОВ ОЙЛ ООД, планира да изгради фотоволтаична електрическа централа (ФтЕЦ), състояща се от фотоволтаични модули, батерии и инвертори, за нуждите на два магазина на ВАНГЕЛОВ ОЙЛ ООД в гр. Враца. 
 Инсталираната мощност на фотоволтаични модули на първия магазин на дружеството, който се намира на гл. път Е-79, посока Мездра-Враца, с. Паволче, местност Дърводелци  е 28 KW, а капацитетът на батериите е 30 KWh. 
А инсталираната мощност на фотоволтаични модули на втория магазин на дружеството, което се намира на гл. път Е-79, посока Враца-Мездра, с. Паволче, местност Крушовишка бара  е 28 KW, а капацитетът на батериите е 30 KWh. 
ФтЕЦ ще бъде разположен на покривните пространтсва на двата магазина.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 27 329.85 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 78 085.27 EUR
Grant 50 755.42 EUR
Self amount 27 329.85 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN