Identification

UMIS Number BG16RFPR001-2.004-2623-C01
Project Name “Improving Energy Efficiency in "ZAI" JSC.
Beneficiary 111004969 ZAI JSC
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 14.04.2026
Start Date 14.04.2026
End Date 14.04.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Монтана (BG312), Берковица, гр.Берковица

Description

Brief description
Дейността на "ЗАИ" АД е производство на дискове за шлайфане и рязане за ръчни инструменти /ъглошлайф/, шмиргели на керамична свръзка и бакелит. Производственият процес на предприятието се характеризира с висока енергийна интензивност на производството. Сградният фонд и част от оборудването на предприятието са амортизирани и не отговарят на съвременните изисквания за енергийна ефективност, което води до високи разходи и топлинни загуби. В настоящото проектно предложение планираме изпълнение на следните мерки за енергийна ефективност и насърчаване използването на енергия от възобновяеми източници, с което да се ускори прехода на предприятието към климатична неутралност:
1. Монтаж на 330 кв.м. енергоефективни изолационни сандвич панели за покрив в съществуващите зони „Абсорбация" и „Тунелна пещ";
2. Подмяна на стари луминисцентни лампи в зона „Абсорбация", зона "Хладилник" и Административна сграда на предприятието с общо 28 бр. енергоспестяващи осветителни тела (тип линейни осветители);
3. Подмяна на съществуващи осветителни тела в участък РМЦ с нови 28 бр. камбанни LED осветителни тела;
4. Подмяна на 85 кв.м. стара метална еднопластова дограма с нова енергоефективна дограма  в административната сграда и склада за готова продукция;
5. Монтаж на 3 бр. термопомпи ( тип "въздух - вода") за замяна на съществуващ пелетен котел в административната сграда на предприятието;

В резултат от изпълнението на планираните дейности по проекта, очакваме да бъдат постигнат следните резултати:
1. Подобрен микроклимат и намалено потребление на енергиен ресурс за отопление, охлаждане и осветление;
2. Повишена конкурентоспособност в резултат на намаляване на разходите за електроенергия за осветление, отопление и климатизация.

Целевите групи по проекта са:
1. Предприятието като стопанска единица, което увеличава ресурсната си ефективност и намалява енергийна си интензивност
2. Заетите в предприятието, за които ще се осигури подобрена работна среда и микроклимат.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 28 336.80 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 79 463.82 EUR
Grant 51 127.02 EUR
Self amount 28 336.80 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка на енергоспестяващи LED осветители – 2 типа (тип камбана и линейни) – общо 56 бр., Estimated Amount: 9 527.41
  • Differentiated position 1: Доставка на енергоспестяващи LED осветители – 2 типа (тип камбана и линейни) – общо 56 бр.
    Contractor:
    Contract total funded value:
Procedure 2 Subject to due process: Доставка на термопомпи тип въздух–вода с топлинна мощност 18 kW – 3 бр., Estimated Amount: 18 602.91
  • Differentiated position 1: Доставка на термопомпи тип въздух–вода с топлинна мощност 18 kW – 3 бр.
    Contractor:
    Contract total funded value:
Procedure 3 Subject to due process: СМР за доставка и монтаж на прозрачни ограждащи конструкции (PVC прозорци и врати) – 85 кв.м., Estimated Amount: 13 057.93
  • Differentiated position 1: СМР за доставка и монтаж на прозрачни ограждащи конструкции (PVC прозорци и врати) – 85 кв.м.
    Contractor:
    Contract total funded value:
Procedure 4 Subject to due process: СМР за изпълнение на топлоизолационна система от сандвич панели за покрив – 330 кв.м., Estimated Amount: 38 275.57
  • Differentiated position 1: СМР за изпълнение на топлоизолационна система от сандвич панели за покрив – 330 кв.м.
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN