Identification

UMIS Number BG16RFPR001-2.004-0562-C01
Project Name Construction of a 215 kWh local battery energy storage system with inverter for self-consumption at “IVAMIT” Ltd., Tsrancha village, Pazardzhik Municipality, aiming to reduce energy costs, improve energy efficiency and increase consumption flexibility.
Beneficiary 202055481 IVAMIT Ltd.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 05.05.2026
Start Date 05.05.2026
End Date 05.05.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пазарджик (BG423), Пазарджик, с.Црънча

Description

Brief description
Проектът предвижда доставка, монтаж и въвеждане в експлоатация на локална система за съхранение на електроенергия за собствено потребление, инсталирана във вътрешната мрежа на „ИВАМИТ“ ЕООД, землище на с. Црънча (ЕКАТТЕ 78570), ПИ № 000521, общ. Пазарджик. Системата е с общ капацитет 215 kWh и интегрирани инвертор с номинална мощност 108 kW (3×400 V, 50/60 Hz, cosφ −1…+1). Батерийната технология е LiFePO₄. Предвидени са всички дейности по доставка, монтаж, настройка, тестване, обучение на персонала, документация и пуск, както и гаранционно обслужване съгласно приложените техн. условия и сертификати (IEC/UL/UN стандарти). Инвестицията попада в допустимата категория „локални съоръжения за съхранение на енергия (батерии) в комбинация с инвертор/и“ по процедура BG16RFPR001-2.004 и ще се реализира в срок до 12 месеца, в съответствие с изискванията за допустимост, публичност, устойчивост и режим de minimis. Системата ще бъде свързана към съществуващата фотоволтаична електроцентрала на предприятието и ще се използва единствено за собствено потребление; не се предвижда продажба на електроенергия. Очаквани резултати: повишаване на енергийната ефективност и гъвкавостта на потреблението (изместване на товар от пикови към извънпикови часове), понижаване на разходите за електроенергия, оптимизиране на натоварването на инсталациите и повишаване надеждността на захранването в производствения процес.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 90 549.00 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 141 678.19 EUR
Grant 51 129.19 EUR
Self amount 90 549.00 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN