| UMIS Number | BG16RFPR001-2.004-2253-C01 |
| Project Name | “Support for energy efficient equipment and the use of energy from renewable sources for the company NET MAG Ltd.” |
| Beneficiary | 205163149 NET MAG LTD |
| Funding | ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027 |
| Date of the Contract/Order | 01.06.2026 |
| Start Date | 01.06.2026 |
| End Date | 01.04.2027 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Настоящият проект има за цел инвестиции за подобряване на енергийната ефективност и насърчаване използването на енергия от възобновяеми източници (ВИ) за собствени нужди в предприятие НЕТ МАГ ЕООД. Дейностите по проекта са насочени към подобряване на енергийната ефективност чрез закупуване на следното оборудване: - Термопомпа въздух - въздух - Слънчеви системи за топла вода и битово горещо водоснабдяване - Фотоволтаична електрическа централа - Енергоспестяващи осветители - Локални съоръжения за съхранение на енергия (батерии) в комбинация с инвертор/и Изпълнението на проекта ще ускори прехода на предприятие НЕТ МАГ ЕООД към климатична неутралност чрез намаляване на въглеродния отпечатък, оптимизиране на енергийната консумация и увеличаване на ВИ в енергийния микс. Очакваните резултати се изразяват в подобряване на енергийната ефективност и увеличаване използването на енергия от възобновяеми източници за собствени нужди. Посоченото може да допринесе както за повишаване на конкурентоспособността и понижаване на енергийната интензивност на предприятието, така както и като цяло за икономиката в региона. |
| Activities | None |
| Partners | None |
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Private investment matching public support (grants, financial instruments)(Transition Region)(SO Energy Efficiency)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 19 886.85 , Reached amount: 0.00 |
| Total Project cost | 56 819.57 EUR |
| Grant | 36 932.72 EUR |
| Self amount | 19 886.85 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 81.16 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Закупуване, доставка и монтаж на енергийно ефективни активи по две обособени позиции - 1. Фотоволтаични панели в комбинация с инвертори - 20 kW и 2. Локални съоръжения за съхранение на енергия (батерии) в комбинация с инвертори - 25 kW“ ,
Estimated Amount: 44 361.81
|
| Procedure 2 |
Subject to due process: Доставка и монтаж на енергоспестяващи осветители - Панели/Луни и Камбани/Прожектори ,
Estimated Amount: 3 169.38
|
| Procedure 3 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на дълготрайни материални активи (ДМА) - Плоски слънчеви колектори - 2 бр.,
Estimated Amount: 3 013.29
|
| Procedure 4 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на дълготрайни материални активи (ДМА) - Термопомпа въздух–въздух 2 бр.,
Estimated Amount: 6 275.08
|
Notes: