Identification

UMIS Number BG16RFPR001-2.004-0621-C01
Project Name Implementation of energy-efficient equipment in the production activities of "Hedon" LTD
Beneficiary 203579259 HEDON OOD
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 31.03.2026
Start Date 31.03.2026
End Date 31.03.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Ловеч (BG315), Троян, гр.Троян

Description

Brief description
Цел на проектното предложение: 
Повишаване конкурентоспособността на  ХЕДОН ЕООД, чрез  оптимизиране на енергийната консумация в производствените процеси  на фирмата.

Проектното предложение включва закупуване и внедряване на енергийно ефективно оборудване за производствени процеси в цех "Фурнирен" и склад готова продукция "фурнир",   Цех производство дъски и детайли и  склад готова  продукция и  ремонтна работилница със склад. 
1.Котел на биомаса с диапазон 465 kw - 1 броя
2.Инверторен компресор за сгъстен въздух  включително резервоари за сгъстен въздух - 1броя.
3. Енергийноефективни осветители - 117 брой линейни осветители и 8 броя камбанни.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 27 480.45 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 78 515.57 EUR
Grant 51 035.12 EUR
Self amount 27 480.45 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на енергоспестяващи осветители, Estimated Amount: 20 938.71
  • Differentiated position 1: Доставка и монтаж на енергоспестяващи осветители
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN