Identification

UMIS Number BG16RFPR001-2.004-1317-C01
Project Name Improving the energy efficiency of GOLD BREAD Ltd. through the implementation of a photovoltaic power plant with local energy storage facilities for self-consumption.
Beneficiary 203303467 Gold Bread Ltd.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 01.06.2026
Start Date 01.06.2026
End Date 01.06.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Стара Загора (BG344), Стара Загора, с.Преславен

Description

Brief description
Проектното предложение на „Голд Бред“ ООД е насочено към подобряване на енергийната ефективност и повишаване дела на използваната енергия от възобновяеми източници чрез изграждане на фотоволтаична централа с инсталирана мощност 40kw в комбинация с локални съоръжения за съхранение на електрическа енергия с общ капацитет 51.2 kw/h за собствени нужди. „Голд Бред“ ООД е предприятие с  дейност производство на хляб, хлебни и пресни сладкарски изделия, при което потреблението на електрическа енергия е значителен разход в производствения процес.Реализирането на проекта ще позволи на предприятието да намали зависимостта си от външни доставчици на електроенергия, да оптимизира енергийната си консумация и да постигне устойчиво намаление на енергийните разходи. Въвеждането на система за производство и съхранение на електроенергия от възобновяеми източници ще допринесе за повишаване на конкурентоспособността на дружеството и  подобряване на енергийната сигурност на дейността му.Проектът ще се изпълнява в рамките на срок до дванадесет месеца и ще има дългосрочен положителен ефект както върху икономическите резултати, така и върху екологичните показатели на предприятието.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 19 521.32 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 55 775.20 EUR
Grant 36 253.88 EUR
Self amount 19 521.32 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN