UMIS Number BG16RFPR001-2.004-2003-C01
Project Name Energy efficiency measures at VEPA 1 Ltd.
Beneficiary 200245232 VEPA-1 LTD.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 05.06.2026
Start Date 05.06.2026
End Date 05.06.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северен централен (BG32), Русе (BG323), Русе, гр.Русе

Description

Brief description
Дейностите по проекта са свързани със закупуване и инсталиране на високо енергийно-ефективни активи, които ще намалят енергийните разходи на компанията и ще допринесът повишаване на енергийната й независимост. 

Енергийно-ефективните мерки, които ще се изпълнят по проекта са : 
 1. Закупуване и инсталиране на фотоволтаична централа на покрива на гаражните и сервизните помещения на фирмата, което ще позволи на компанията да произвежда и използва за собствени нужди генерираната енергия от слънцето. Батерийният блок ще позволи произведената енергия да се съхрани и използва при необходимост
 2. Закупуване и инсталиране на две секционни индустриални врати, които ще се монтират в двата края на индустриалното хале. По този начин ще се намалят топлинните загуби при отваряне/затваряне на вратата и ще се осигури по-добра изолация и по-ниски енергийни загуби. Секционните врати с механизма си на отваряне/затваряне ще доведат до повишена безопасност и функционалност при използването им, както и  по-ниски разходи за експлоатация и поддръжка.
Закупените по проекта активи ще допринесат за подобряване на енергийната ефективност на омпанията и ще допринесат за  подобряване на екологичните цели на предприятието.

Инвестициите по проекта са  стратегическа стъпка към устойчиво, икономично и модерно производство, ще намалят производствените разходи  и ще допринесат за повишаване на конкурентоспособността на компанията.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 16 454.36 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 47 012.46 EUR
Grant 30 558.10 EUR
Self amount 16 454.36 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN