Identification

UMIS Number BG16RFPR001-2.004-1175-C01
Project Name Energy efficiency improvement at KMS JSC
Beneficiary 207387391 KMC
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 23.03.2026
Start Date 23.03.2026
End Date 23.03.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Враца (BG313), Козлодуй, гр.Козлодуй

Description

Brief description
Проектът цели повишаване на енергийната ефективност и енергийната самостоятелност на производствения обект на кандидата (работилница) чрез изграждане на ФЕЦ и подмяна на компресор. Потребността произтича от високите енергийни разходи и от необходимостта от по-надеждно и предвидимо енергоснабдяване и изисквания за декарбонизация.
Целева група по проекта са местната общност поради по-ниските емисии.
Основните цели са:
- Намаляване на енергопотреблението чрез подмяна на компресор.
- Производство на чиста електроенергия на място и повишаване на самостоятелността чрез ФЕЦ.
Очакваните резултати от реализация на проекта са:
1. Намаляване на енергийните разходи за експлоатация на компресор;
2. Покриване на част от собственото електропотребление от ВЕИ, намалени емисии CO2 и по-нисък въглероден отпечатък.
3. Повишена конкурентоспособност и устойчивост на дейността.
Основни дейности са:
- Изграждане на покривна ФЕЦ за собствено потребление.
- Доставка и монтаж на окомплектован компресор.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 28 240.18 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 79 369.37 EUR
Grant 51 129.19 EUR
Self amount 28 240.18 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка на ново енергийно ефективно оборудване, свързано с производствения процес, Estimated Amount: 26 121.90
  • Differentiated position 1: Компресор за сгъстен въздух - 1 брой
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN