Identification

UMIS Number BG16RFPR001-2.004-0197-C01
Project Name Energy Efficiency Investment through Construction of a 100 kW Photovoltaic Power Plant for Own Consumption at Plastform Ltd
Beneficiary 107010172 Plastform OOD
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 18.03.2026
Start Date 18.03.2026
End Date 18.03.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северен централен (BG32), Габрово (BG322), Габрово, гр.Габрово

Description

Brief description
Проектното предложение предвижда изграждане и въвеждане в експлоатация на фотоволтаична електроцентрала (ФтЕЦ) с мощност 100 kW, предназначена за покриване на собствените енергийни нужди на Пластформ ООД. Съоръжението ще бъде изградено върху собствен терен – паркинг на дружеството, като по този начин се оптимизира използването на наличната площ, без да се засягат производствени или зелени зони.

Основната цел на проекта е постигане на по-висока енергийна ефективност чрез намаляване на зависимостта от външни доставчици на електроенергия и осигуряване на стабилно и устойчиво енергийно захранване за производствените процеси. Очакваният ефект е значително редуциране на енергийните разходи, подобряване на енергийната независимост на предприятието и повишаване на конкурентоспособността му в условията на растящи енергийни предизвикателства.

Използването на възобновяем източник – слънчева енергия – ще допринесе за ограничаване на въглеродния отпечатък и за намаляване на емисиите на парникови газове, което е в съответствие с националните и европейски приоритети за зелена трансформация и климатична неутралност. Реализацията на проекта ще има положителен ефект не само за дружеството, но и за регионалната икономика, като съчетава технологични иновации, устойчиво производство и отговорно управление на ресурсите.

С изпълнението на проекта предприятието ще постигне намаляване на консумацията на електроенергия с 10% спрямо базовата линия, както и редукция на емисиите на CO₂ с 50 тона годишно. Инвестицията е в пълно съответствие с принципа DNSH („Do No Significant Harm”), като във всички етапи – доставка, монтаж и експлоатация – са предвидени мерки за минимизиране на отпадъците, намаляване на емисиите от прах и контрол върху въздействието върху екосистемите
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 88 308.80 , Reached amount: 0.00
Indicator 2 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 139 437.99 EUR
Grant 51 129.19 EUR
Self amount 88 308.80 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка на ДМА за енергийна ефективност: Фотоволтаична електрическа централа ФтЕЦ - 1 брой , Estimated Amount: 139 437.99
  • Differentiated position 1: Доставка на ДМА за енергийна ефективност: Фотоволтаична електрическа централа ФтЕЦ - 1 брой
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN