Identification

UMIS Number BG16RFPR001-2.004-2183-C01
Project Name Improving Energy Efficiency and Use of Renewable Energy at Tashev Trans Ltd through Installation of a Photovoltaic System with Battery Storage and an Energy-Efficient Chiller in Vratsa.
Beneficiary 106521623 TASHEV-TRANS
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 20.04.2026
Start Date 20.04.2026
End Date 20.04.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Враца (BG313), Враца, гр.Враца

Description

Brief description
Проектното предложение на „Ташев Транс“ ООД предвижда инвестиция в зелена енергия и енергийна ефективност, чрез закупуване и инсталиране на фотоволтаична система с мощност 50 kW, батериен модул за съхранение на електроенергия, както и чилър с мощност 60 kW за охлаждане на административните и сервизни помещения. Системата ще се използва изцяло за собствени нужди, без продажба на енергия.
Инвестицията ще позволи намаляване на енергийното потребление от невъзобновяеми източници, ще осигури енергийна независимост и по-ниски експлоатационни разходи, като същевременно ще има съществен екологичен ефект чрез редуциране на въглеродните емисии и оптимизация на енергийните процеси.
Реализацията на проекта ще повиши конкурентоспособността на дружеството и ще допринесе за устойчивото развитие на Северозападния регион, един от най-слабо развитите в страната и ЕС. Инициативата напълно съответства на целите на процедурата BG16RFPR001-2.004, като подпомага прехода към икономика с ниски въглеродни емисии и ефективно използване на природните ресурси.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Private investment matching public support (grants, financial instruments)(Less developed Region)(SO Energy Efficiency)(PCIE 2021-2027)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 33 367.70 , Reached amount: 0.00
Indicator 3 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 84 475.19 EUR
Grant 51 107.49 EUR
Self amount 33 367.70 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN