Identification

UMIS Number BG16RFPR001-2.004-0230-C01
Project Name Improving the Energy Efficiency of ELEGANT LT Ltd.
Beneficiary 109573269 ELEGANT LT Ltd.
Funding ERDF ==> Programme "Competitiveness and Innovation in Enterprises" 2021-2027
Date of the Contract/Order 01.06.2026
Start Date 01.06.2026
End Date 01.06.2027
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Град (BG411), Столична, гр.София

Description

Brief description
Проектното предложение на „Елегант ЛТ“ ООД предвижда изграждане на фотоволтаична електрическа централа с инсталирана мощност на инверторите 60 kW за собствено потребление. Основната цел е повишаване на енергийната ефективност и намаляване на разходите за електроенергия, използвана в производствените процеси на дружеството.

Изпълнението на проекта ще се осъществи на база предварително изготвен технически проект, който определя оптималното проектиране и монтаж на системата. За да се гарантира безопасност и дълготрайност на инсталацията, ще бъде извършена реконструкция на покривната конструкция, така че тя да отговаря на всички технически и нормативни изисквания за поставяне на фотоволтаични модули.

Фотоволтаичната централа ще бъде изградена върху наета производствена сграда, за която „Елегант ЛТ“ ООД разполага с дългосрочен договор за наем и учредено право на строеж. Партидата за електрозахранване е на името на дружеството, което осигурява възможност за директно присъединяване на системата и използване на произведената електроенергия за собствени нужди.

Чрез реализиране на проекта „Елегант ЛТ“ ООД ще постигне значително намаляване на енергийното потребление от външни източници, ще ограничи въглеродните емисии и ще повиши устойчивостта и конкурентоспособността си в дългосрочен план.
Activities None

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Enterprises supported by grants, Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Enterprises supported (of which: micro, small, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 3 Private investment matching public support (grants, financial instruments)(Transition Region)(SO Energy Efficiency)(PO2), Measure Unit: EUR, Base Value: 0.00 , Target amount: 32 533.60 , Reached amount: 0.00

Financial Information

Total Project cost 83 662.79 EUR
Grant 51 129.19 EUR
Self amount 32 533.60 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 81.16 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Изграждане и въвеждане в експлоатация на фотоволтаична електрическа централа за собствено потребление, Estimated Amount: 83 662.79

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN