| UMIS Number | BG05SFPR001-4.002-0002-C01 |
| Project Name | Qualification for Strengthening the Capacity of Educational Leaders for Effective Development and Management of European Projects |
| Beneficiary | 175134459 National Center for the Improvement of the Qualification of the Pedagogical Specialists |
| Funding | ESF+ ==> Programme "Education" 2021-2027 |
| Date of the Contract/Order | 01.07.2025 |
| Start Date | 01.07.2025 |
| End Date | 01.11.2028 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът има за цел да повиши квалификацията на ръководителите на образователните институции в системата на предучилищното и училищното образование, по отношение на подготовката и ефективното управление на европейски проекти. Чрез обучения участниците ще развият основни умения в планирането, изпълнението, мониторинга и отчитането на проекти, финансирани със средства от ЕФСУ/ЕСФ+. Проектът се фокусира върху справянето с ключовите предизвикателства, срещнати по време на предишните програмни периоди и обучението на ръководния персонал в детските градини и училища с необходимите умения за ефективно управление на стратегическите операции в техните институции. Чрез насърчаване на подобрена административна способност за управление на проекти, този проект цели да осигури ефективно и успешно изпълнение на операциите от стратегическо значение по Програма “Образование” 2021 – 2027 г. (ПО) и постигане на целите на политиките на ЕС. |
| Activities |
|
| Partners | None |
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Number of schools and kindergartens trained under the programme (Transition region), Measure Unit: Number, Base Value: 0.00 , Target amount: 211.00 , Reached amount: 0.00 |
| Indicator 2 | Trained representatives of beneficiaries/partners/target groups and of potential beneficiaries/partners/target groups, Measure Unit: Number, Base Value: 0.00 , Target amount: 423.00 , Reached amount: 0.00 |
| Indicator 3 | Number of schools and kindergartens trained under the programme (Less developed regions), Measure Unit: Number, Base Value: 0.00 , Target amount: 1 057.00 , Reached amount: 0.00 |
| Indicator 4 | Trained representatives of beneficiaries/partners/target groups and of potential beneficiaries/partners/target groups, Measure Unit: Number, Base Value: 0.00 , Target amount: 2 113.00 , Reached amount: 0.00 |
| Total Project cost | 511 160.88 EUR |
| Grant | 511 160.88 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 102 231.78 EUR |
| Percentage of EU co-financing | 82.49 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| There are no tender procedures |
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN