| UMIS Number | BG05SFPR002-1.004-1778-C01 |
| Project Name | Improvement of working conditions in "MULTI-PROFILE HOSPITAL FOR ACTIVE TREATMENT - DOBRICH" AD |
| Beneficiary | 124141302 MNOGOPROFILNA BOLNIZA ZA AKTIVNO LECHENIE - DOBRICH AD |
| Funding | ESF+ ==> Human Resources Development 2021-2027 |
| Date of the Contract/Order | 05.12.2024 |
| Start Date | 05.12.2024 |
| End Date | 05.12.2025 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
В проекта са включени следните дейности: 1. Дейност за разработване на зелен модел за организация на дейността и за разработване и въвеждане на „зелени“ карти за работните места – обхваща всички 534 служители; 2. Подобряване на здравословните и безопасни условия на труд чрез закупуване на нови и по-модерни средства за колективна защита, свързани със специфични рискове за БЗР за работещите, а именно – предотвратяване на заразяване от биологични агенти чрез осигуряване на ефективно пречистване на въздуха в помещения. Чрез тях се преодоляват идентифицирани проблеми в оценката на риска и се подобряват значително условията на труд за работещите на тези длъжности. Ще бъде осигурено управление на проекта, което да осигури спазването на приложимите нормативни и други изисквания, и ефективно постигане на целите и очакваните резултати. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Employed, incl. self-employed, Measure Unit: Number, Base Value: 0.00 , Target amount: 534.00 , Reached amount: 493.00 |
| Total Project cost | 232 396.99 EUR |
| Grant | 185 917.59 EUR |
| Self amount | 46 479.40 EUR |
| Total actual amounts paid | 185 248.00 EUR |
| Percentage of EU co-financing | 83.81 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Доставка и монтаж на средства за колективна защита“,
Estimated Amount: 327 673.50
|
| Procedure 2 |
Subject to due process: Разработване и прилагане на „зелени“ модели на организация на труд съобразно спецификата на конкретните работни места в предприятията. Изготвяне на „зелени“ карти за организация на работни процеси на конкретните работни места. Обучение на лицата от целевата група насочено към внедряване на „зелени“ модели на организация на труд,
Estimated Amount: 16 666.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN